00:31 Due to the wear of the rail, there's a need to change out when it hits a certain threshold.
00:35 So the consist team is out here tonight to do up the rail change.
00:38 Essentially, we cut out the part that the worn rail and we replace it with another new rail.
00:48 And to do this effectively, you will have to do the welding on both sides as well.
00:52 So that whole process takes that time and typically every night we only have about three hours to complete the whole process.
01:00 We have about 18 to 16 workforce of SMRT staff as well as our integrated workforce.
01:06 Given the age of the North-South-East-West line, actually we are deploying up to five work fronts or five teams every night to do up a rail change.
01:16 Every rail change can be up to 18 to 36 metres. So every night you can say we change out about 100 metres of rail.
01:25 The rail change part is really critical for ensuring the safety of the rail system as well as the comfort of the ride.
01:32 Track renewal is very interesting to me because it's literally the tracks that we are working on.
01:42 Trains can't run without the tracks.
01:44 So the challenges we face every night probably is the time constraint.
01:47 We will start around 1.30am and we have to stop latest by 4.30am.
01:52 But of course we overcome these challenges by having a strict procedure that we always follow to make sure that we carry out our rail replacements in time.
02:01 I feel that our work is considered behind the scenes.
02:07 I think not many people would know that because the work we do is between 1.30am to 4.30am.
02:13 So the commuters and the public do not get to see it.