DOTr, hindi na nagulat sa panibagong tigil-pasada ng Manibela; Partial Operability ng North South Commuter Railway, tuloy sa December 2027

Transcript
00:00The Tigil Pasada, which is owned by Tutol Group, will be accompanied by the Transportation Department in the PUV modernization.
00:08This is what Ryan Leziguez reported.
00:11The Transportation Department is no longer alarmed by the new Tigil Pasada,
00:16which is owned today by the Manibela Group, which will last until Wednesday.
00:20DOTR Secretary Jaime Bautista said that the public is used to the left and right transport strike,
00:27which does not affect the riding public.
00:30Bautista said that the protest will only last until the next day,
00:35when they will cancel the crackdown on the unconsolidated PUVs.
00:40The opening of the modernization program will continue.
00:43We are used to the threat of Manibela.
00:46We saw that their previous strikes did not affect us.
00:54That only means that our public transport modernization program is working,
01:01because the majority, 83%, already supported the program.
01:07Kalihim said that the PUV modernization program is not perfect,
01:12but for now, many are benefitting from it.
01:16Bautista said that,
01:17along with the inspection of the Clark-Pampanga Depot of the North-South Commuter Railway,
01:22or NSCR, which is 81.69% completed,
01:26the NSCR's partial operability will continue in December 2027.
01:32The Clark Depot has an area of 33 hectares,
01:35which has a stabling yard, integral bridge, and 48 depot buildings and facilities
01:41that are important for the operation of the entire NSCR alignment.
01:45The Clark Depot is under the Contract Package CPN-05.
01:50Structural, mechanical, electrical, and mechanical works are almost completed.
01:57The waterproofing of panel installations, gutters, and drywalls for the workshop,
02:04light repair shop, operations control center, and training center is almost complete.
02:08The Clark Depot will serve as the major depot of the NSCR project,
02:13which is based on the interoperability of the entire alignment from Clark-Pampanga to Laguna.
02:18The NSCR project has a length of 147 kilometers and has 35 stations.
02:25What we are seeing now is the two-storey industrial-type building
02:29that will serve as the NSCR's workshop depot.
02:31For now, 87.35% of this house is completed.
02:36Here, the construction of the NSCR's damaged trains will be done.
02:40The target is to finish this entire depot by June 2025.
02:45This is really designed to conform with global standards.
02:49And this is the reason why JICA is supporting it.
02:54Because this is funded by JICA, we see to it that this conforms with global standards.
03:03The traffic in Metro Manila and Karating Province is expanding
03:08as all railway projects in the country are coming to an end.
03:12Including the NSCR and Metro Manila Subway Project.
03:15These are also planned to be connected.
03:18Our subway will connect with LRT2 and also NSCR.
03:26They will meet in Bicutan.
03:29Actually, that is our dream.
03:33That our train system will be similar to the operations of trains in Japan or other developed countries.
03:45Ryan Lizigas for Pambansang TV in Bagong, Philippines.