Skip to playerSkip to main content
  • 6 hours ago
Meta is revealed as the company behind a 2,000-acre Kentucky data center while residents sue, Alabama approves a $1.15 billion tax break, and federal regulators reject PJM's data center grid plan. Here's what happened across U.S. data centers:

🏘️ COMMUNITY — Meta Revealed Behind 2,000-Acre Kentucky Data Center. Residents of Mason County have two lawsuits pending as the $15 billion project nears closing. Initial investment about $15 billion; attorney says it could grow far larger over a 40-year, multiphase life. Meta expected to close on the land in November and will seek state tax exemptions. Group We Are Mason County KY says buyout offers never materialized and low-frequency noise rules were refused.

🏘️ COMMUNITY — Alabama County Grants $1.15B Tax Break to Mystery Data Center. Lowndes County approved Project Red Clay early, and its end user is still unnamed. 20-year abatement worth about $57.5 million a year for Project Red Clay. Site requested 1,500 MW from Alabama Power along the Selma to Montgomery trail. District Judge Adrian Johnson, a future neighbor, blasted the lack of transparency.

⚖️ LEGAL — Judge Tosses Three DC Blox Claims in Nashville Zoo Data Center Fight. The federal judge also denied the developer's request for a preliminary injunction. Three of nine claims dismissed; company has 21 days to amend its complaint. DC Blox sued in August over Nashville's moratorium and halted permits next to the zoo. Zoo petition against the project has more than 600,000 signatures.

⚡ POWER — FERC Rejects PJM's Plan to Connect Data Centers to the Grid. Regulators struck down the core of the nation's largest grid operator's large-load proposal. Rejected the Interim Resource Adequacy Service that would curtail large loads before emergencies. Approved only PJM's large-load definition and registry. Jefferies: higher capacity prices could last longer; states, including Ohio and Pennsylvania, may lead.

💧 WATER — Georgia Plant for Data Centers Would Pull 1M Gallons Daily

Category

🤖
Tech
Transcript
00:00A fight over farmland in Kentucky now has Meta's name on it.
00:04With a $15 billion starting price tag from Alabama tax breaks to a Nashville courtroom
00:11and a federal ruling that shakes up the nation's biggest grid.
00:16Here is what is happening.
00:18A fight over farmland in northern Kentucky just got a very big name attached to it.
00:25Meta has been revealed as the company behind a 2,000-acre hyperscale campus in Maysville.
00:31In Mason County, with an initial investment of about $15 billion,
00:37an attorney for the project says it could eventually grow far beyond that over a 40-year
00:42multi-phase life.
00:45Meta is expected to close on the property in November and will seek state tax exemptions.
00:50Supporters point to 2,000 construction jobs and at least 400 permanent positions.
00:57But the citizens group We Are Mason County KY has two lawsuits pending.
01:03Seeking transparency and farmland preservation,
01:07Executive Director Max Moran says the county declined low-frequency noise rules,
01:13set a 750-foot setback from homes,
01:17and has not delivered promised buyout offers.
01:21That kind of local friction is playing out in Alabama, too,
01:25where commissioners in Londies County approved a 20-year,
01:29$1.15 billion tax abatement for Project Red Clay,
01:34billed as the state's largest planned data center.
01:38The vote came on a Tuesday morning,
01:40earlier than the October 20th date on the agenda.
01:43The site sits along the Selma to Montgomery Trail in unincorporated territory where the county has
01:50no zoning authority,
01:52and the project has requested 1,500 megawatts from Alabama power.
01:58Developer Cloverleaf Infrastructure projects $124 million a year in
02:04local tax revenue,
02:06but the abatement costs about $57 million annually.
02:11District Judge Adrian Johnson,
02:13a future neighbor,
02:15criticized the lack of transparency,
02:17and the end user has still not been named.
02:20Construction is expected to begin in early 2027.
02:25That opposition is now making its way into courtrooms in Nashville.
02:30A federal judge dismissed three of nine claims D.C. Blocks brought against Metro government over a
02:36proposed data center next to the Nashville Zoo
02:40and denied the company's request for a preliminary injunction.
02:44The judge said some claims were too unclear about what rights the company says Metro took away.
02:50D.C. Blocks sued in August,
02:53challenging the city's data center moratorium and a halt in permit processing,
02:58and argues the site once operated as a data center under tenant Asurian.
03:04Its claims include due process,
03:07equal protection and takings.
03:09The company now has 21 days to amend its complaint.
03:13Meanwhile,
03:14a zoo petition against the project has gathered more than 600,000 signatures.
03:20And council member Courtney Johnston says Metro has the right to set land use decisions.
03:27And the reason this fight keeps gaining momentum comes down to one thing.
03:32Power.
03:34Federal regulators have rejected the core of PJM Interconnection's plan
03:38for connecting large loads.
03:41Like data centers on the nation's largest grid,
03:44the proposal, called the Interim Resource Adequacy Service,
03:49would have let big loads connect without matching new capacity if they agreed to be curtailed.
03:54Before grid emergencies.
03:57Before grid emergencies.
03:57F.E.R.C. said it appears to intrude on state authority over retail customers and may be discriminatory.
04:05While approving PJM's definition and registry of large loads,
04:09Commissioner Rosner warned that non-critical data centers should be curtailed before homes,
04:15hospitals and schools.
04:17Jeffery's analysts say higher capacity prices could last longer.
04:22Benefiting Constellation, NRG,
04:26Tallinn and Vistra,
04:27and that states,
04:28including Ohio and Pennsylvania,
04:31may now take the lead.
04:33The pressure on the grid is only half the story.
04:37Water tells the other half.
04:39In Georgia,
04:40a Georgia tech researcher estimates that generating a data center's electricity uses about 10
04:46times more water than cooling it on site.
04:50In Mitchell County,
04:52NextEra proposed a 1500-megawatt gas plant that would draw about 1 million gallons a
04:58day from the Claiborne Aquifer.
05:01And resident Lauren Dormany is among those challenging the rezoning in Superior Court.
05:06In Rockdale County,
05:09commissioners rejected the rezoning for Project Rockforge.
05:13Altamaha riverkeeper Fletcher Sams says 33 data center campuses are proposed in the
05:19Osimulgee Basin,
05:21where Georgia Power's plant shearer is permitted to draw over 200 million gallons a day.
05:27In a region of about 650,000 people,
05:32local lawmakers are taking notice.
05:34In Clarksville's Montgomery County,
05:38Tennessee,
05:39commissioners approved tight new rules for future data centers on Monday.
05:43The minimum setback from homes was raised from 100 feet to 500 feet by amendment.
05:50Applicants must keep noise within 3 decibels of ambient levels and below 55 decibels at
05:56neighboring property lines.
05:59They must also provide letters from water,
06:02power and gas providers confirming they can be served,
06:06pay for needed utility upgrades,
06:08and build on sites of 10 to 100 acres.
06:12Commissioners discussed postponing the resolution and a moratorium,
06:16but neither passed.
06:18Regional Planning Director Jeff Tindall has said similar rules could go to the Clarksville City
06:23Council if they are well received.
06:27Yet despite that regulatory wave,
06:30construction is pressing forward.
06:33In Taylor,
06:34Texas,
06:35City Council unanimously approved the Taylor Technology Campus from Powerhouse and Big Watt Digital.
06:42Formerly known as Project Mustang,
06:44The site covers 664 acres in Williamson County,
06:49about 35 miles northeast of Austin,
06:53with up to 1 gigawatt of capacity and a first phase of 500 megawatts.
06:58It would run on dedicated behind-the-meter power from a new 750-megawatt natural
07:04gas plant,
07:06with first power targeted for the first half of 2028.
07:10The site reportedly will use closed-loop cooling to reduce water use.
07:16Powerhouse,
07:17a division of American real estate partners,
07:20has a pipeline of more than 8 gigawatts,
07:23and Brookfield recently took a minority stake.
07:27And the financial commitment behind that construction is staggering.
07:32Yet so are the obstacles.
07:34Industry research finds 30-50% of the 16 gigawatts of U.S. data center.
07:41Capacity scheduled to come online faces severe delays or cancellation.
07:46Generator step-up transformer lead times now exceed 160 weeks.
07:52And about 80% of U.S. power transformer demand is met by imports.
07:58Allian's research points to a shortage of roughly 439,000 skilled.
08:03Construction workers in big markets waits for a firm power commitment run 4-7 years.
08:11And more than 100 moratoria are active.
08:15Oracle and OpenAI scrapped a plan to expand the Abilene, Texas campus from 1.2 to 2 gigawatts.
08:23Meanwhile, U.S. construction spending has reached $85.3 billion.
08:37It helps us cover more of these stories.

Recommended