00:00With three active train lines, this is now the network of trends in Metro Manila.
00:10But this is what the Japan International Cooperation Agency, or JICA, proposed in 1973.
00:17Along with a subway.
00:22Finally, after five decades, the underground train system is being built.
00:27And we have an exclusive update.
00:32To see is to believe.
00:34And we are now here in Valenzuela, Vipo.
00:39The only permanent thing we see here are these tunnel rings.
00:44The rest is just for construction, including our ventilation, our railings right here.
00:50Everything we see here, including the conveyor belt, is all used for construction.
00:57East Valenzuela has only one of 17 stations.
01:00In eight cities, with three central business districts.
01:05Just a quick update for our viewers.
01:08They have 15% physical progress.
01:12And behind me right now, this is our tunnel boring machine.
01:16This is where it starts, and this is where it continues.
01:20We are currently in the middle of East Valenzuela and Quirino stations.
01:26So we are in the middle.
01:28And up until this point, from where we left off earlier in Valenzuela, Vipo, up until now,
01:35they have already drilled 1.1 kilometers.
01:39We also arrived at the part of the subway that you wouldn't believe is under a river.
01:46The tunnel that we are building right now, it goes through Mindanao Avenue.
01:53Is it safe to construct a structure like this under the river?
01:59Actually, in between our segments, it has a rubber gasket, which is watertight.
02:05And we maintain an oxygen level here.
02:08We have detection for, for example, earthquakes.
02:13It also has control measures for floods.
02:17This is important because the average depth of the subway is 30 meters,
02:22which is as high as a typical nine-story building.
02:28We also got to see the inside of the tunnel boring machine,
02:31or the machine that digs and puts segment rings that will be built in the tunnel.
02:37From its cockpit, which also serves as the control center of the tunnel construction,
02:41to the chamber where the tunnel rings are built with six panel segments.
02:47The five in the back are the long ones, the big ones.
02:51Those are the main parts of our tunnel ring.
02:53The sixth part that will be built of our panel segments is here.
03:01This is where the sixth part will go.
03:03It will be the specific lock of our tunnel ring.
03:07In other words, in the puzzle, it is the final piece of the puzzle
03:11so that our rings will be solid.
03:19When this project is finished,
03:21it will change the public transport system here in the Philippines.
03:26For GMA Integrated News, I'm Martin Avere, Changing the Game!