00:00Hello, how are you, dear brother, dear sister?
00:15Today we begin our 8th session of the subject Integrative Project.
00:22It has truly been very gratifying for me to see that, even if perhaps slowly, we have been progressing, we have been moving forward in this project.
00:38Perhaps the way we are viewing the project today is very different from how we viewed it 3 or 4 sessions ago.
00:48So we see that little by little it is taking on a little more shape.
00:55But that's how a process is; it takes time, it takes time to mature.
01:01But it's always important to keep practicing, reviewing the material, and checking the process we're following.
01:10and applying each of the steps we have seen in the previous sessions to your specific project.
01:20I hope that by now you have made better progress, and that you have already defined your project using the SMART method.
01:31that you have made the list of activities, that you have refined those activities, and that you have also estimated the time required to complete each one of them.
01:49and the cost of each of them, in the same way that you have put a sequential order in the chronology as you are going to carry them out.
02:03Remember that this will help us because it will be the basis for continuing with the Gantt chart, which will allow us to better control the project.
02:22We are now beginning session number 8, in which we will address or review steps number 9 through number 12.
02:37It is very important that you review each of the steps, as we mentioned before, in detail and apply them to your project.
02:49Step number 9 involves monitoring the progress of the project.
02:56In this session we are going to learn what steps 9, 10, 11 and 12 consist of.
03:06We are not going to execute them.
03:10Remember that our execution phase begins from session 9 to session 12.
03:17So, in session 9, it is assumed that when we are already in session 9, we already have our project in the work plan.
03:28We already have the list of activities, we already have the time it will take us, and we will start working on the execution of the project from that session onwards.
03:40So, from session 9 to session 12, we're going to review how we carried out these steps 9, 10, 11, and 12.
03:53The idea is that by session 12 we will have the project fully advanced and, if possible, completed.
04:05And if it's not possible for us to have the execution, we will already have a good understanding of the path we need to follow to make a successful execution.
04:14Let's move on to step number 9 in the topic of monitoring project progress.
04:24In this step number 9 we are going to use what we have already worked on.
04:29Since these are sequential steps from step number 1 to step number 12, we always use the material that we have gathered in the previous steps.
04:45So, it doesn't get so complex each time, but on the contrary, it becomes a little more controlled.
04:53As I was saying earlier, it gives us greater clarity.
04:57Here we will use, for example, the Gantt chart we made, where we put the list of tasks, the time it would take to complete them, and their cost.
05:12These weeks represent the time for each task, and the sum of 35, as we mentioned in the last session, corresponds to the numerical sum of these weeks. However, when we graph in Gantt, when we use Gantt, we can combine some of the activities so that from here, out of 35 weeks, I go down to 13 weeks.
05:38We also said that the maximum recommended time is 15 to 16 weeks.
05:47So, in this case, the project is within the recommended timeframe.
05:52If in your case the project is not on schedule, well, we need to see what adjustments we can make before saying this is the scope and quality of the project.
06:02Because once we have defined and established the scope, it is important to consider that we will no longer modify that project and that scope.
06:15We may have to move the activities or establish some strategies along the way, which we will get to know and learn in our sessions 9 to 12.
06:28In sessions 9 through 12, we will not only be reviewing and monitoring the progress of the project, but we will also hear testimonies from some brothers who have already gone through these processes.
06:45or who have experience in the subject of processes or who have experience in the subject of project management, especially in the matter of Christian projects, in the matter of projects that seek to give glory to the Lord.
06:58Therefore, what we need to do now is monitor the progress of the project.
07:07How are we going to supervise?
07:09Our basis will be this Gantt chart.
07:13As we mentioned in the first sessions regarding the Gantt chart, you can make it on a computer or you can also make it on a sheet of paper.
07:24In this case I want to show it on the computer, but, and this comes from an Excel sheet, you can also do it on a sheet of paper without any problem.
07:37So how are we going to control the project?
07:40Well, here we already have in each of the activities the person responsible for the project and the time in which the project will be carried out.
07:50It doesn't have dates here yet, it says it's week 1.
07:54We haven't defined when week 1 will start.
07:58We will establish that definition once we have the project approved and decided that this is the project we are going to work on.
08:09From that moment on we establish what week 1 is and we give it a specific date.
08:15For example, here I can say that week 1 is March 1st.
08:19So I'll set dates and I know that from the week of March 1st to maybe the week of April 10th, something like week 5,
08:31That's when I have to do the search for a location.
08:34Since I already have my Gantt chart, with the time for each of the activities, this will allow me to keep track.
08:43Once I'm implementing it, it will allow me to keep track of my project.
08:49How am I going to control it?
08:52Well, what I'm going to do is use a color code.
08:55The color code I'm going to use would be the blue I have here, which means that the activity is still on time, that it's not delayed.
09:06that the time I have to be doing it hasn't started yet.
09:11And if I've already started, then I'm going to use, if the activity is in progress, I've already started it, I've already begun working on it, I'll put that it's in progress.
09:25And the color code would be green.
09:29The green would indicate to me that the activity is in progress.
09:32Then, if the project is behind schedule or the specific activity is behind schedule, I use a yellow color code.
09:42In other words, instead of a blue or green square, I put a yellow square.
09:48If that's not the case, then, and if the project or activity is not only behind schedule but also at risk because I haven't done anything completely about it,
10:03So I have to give it a red color.
10:06The color red indicates that this activity is at risk.
10:10If that happens, what I definitely need to do is find a way to accelerate that activity.
10:21that I get involved in that activity to start working on it.
10:25Let's take the example that we are already in week number 4 and that in the area of the activity of searching for the premises,
10:35I marked the first three weeks in yellow because I didn't make much progress.
10:43I went very slowly in this activity and that meant that I had to mark it here with the code or the yellow color.
10:52But by the fourth week it's still late, so I change the color and make it red.
10:59That's a red flag. The point is that my Gantt chart should allow me to see the status of my project at a glance.
11:09to monitor it, to focus the efforts on those points that are falling behind and that may be critical for the project.
11:19So, in this same example, if we are in week 4, on the topic of volunteers, look at what happens here.
11:27By week 4 I had already secured all the volunteers I had planned for.
11:35So, here I can even mark week 5 in green, which hasn't started yet.
11:45That way, I can give this activity a final push and not worry about it anymore.
11:54Therefore, this color allows me to see that the greens are checkmarks and I no longer worry about that because everything turned out very well.
12:08I focus on the reds and continue to attend to the blues.
12:14Or if there's a yellow one, I'll pay attention to it too.
12:17What happens in the case of the kitchen?
12:20In the case of the kitchen, I haven't finished it yet, but I'm on schedule.
12:25In other words, I still have a week and I've already made enough progress in the first week.
12:29The same applies to utensils.
12:31So, it's important that you fully apply this to your project, but for that, I insist, you need to have your activities listed, your project already outlined in the GAN chart.
12:49Which, I insist, can be through the use of an electronic system or spreadsheet, or through a sheet of paper, or however best suits you.
13:02The point is that if you need it, if it's a sheet of paper, then preferably it should be graph paper so you don't struggle with marking the colors here.
13:14But you can do it practically the same way.
13:17On a grid sheet you can put your tasks, the weeks, the costs, the responsible parties and then here each of the weeks in which you are carrying out the activities and the week in which you plan to launch your project.
13:35So, review all of this, apply it to your project, and that will definitely help you learn how to control the project.
13:49I insist, at this point you are not going to apply this yet because you will do that once we are already in the execution process.
14:00But it's something that has to happen very soon.
14:04In fact, in the next session we will talk precisely about the execution and we already need to be working very hard on the project.
14:16That's why it's important that you already have your list of activities, your calculation or estimate of the costs and time, and that you've also gone through the process of seeing if you can accelerate that project.
14:34How can you reduce the number of weeks so that those weeks are no more than the 15 or 16 that we recommend as the maximum limit?
14:47I'll see you in the next video where we'll review steps 10 and 11, and in the following video of this same session, the instructor will possibly finish reviewing steps 11 and 12.
15:04Goodbye, God bless you.