Learn How to Create a Track Corridor Using Autodesk Dynamo in Civil 3D with this step-by-step Railway Design and BIM Modeling tutorial.

In this tutorial, you will learn about creating a railway track corridor using Dynamo and understand its role in Civil 3D transportation infrastructure workflows. Discover how Autodesk Dynamo supports railway corridor modeling, BIM automation, and infrastructure design.

Topics Covered:
- How to Create a Track Corridor Using Dynamo
- Autodesk Dynamo for Civil 3D
- Railway Track Corridor Creation
- Civil 3D Railway Corridor Modeling
- Dynamo for Railway Design
- Railway BIM Modeling
- Transportation Infrastructure Design
- Dynamo BIM Automation

This tutorial is useful for Civil Engineers, BIM Modelers, Railway Designers, CAD Technicians, and Infrastructure Professionals.

Subscribe to Autodesk 786 for more Autodesk Dynamo, Civil 3D, BIM Modeling, Railway Design, Road Design, and Infrastructure Engineering tutorials.

Watch, Learn and Improve Your Autodesk Skills!

#AutodeskDynamo #Civil3D #TrackCorridor #RailwayDesign #DynamoForCivil3D #RailwayBIM #BIMModeling #DynamoTutorial #InfrastructureDesign #TransportationEngineering #Autodesk786 #BIMAutomation
Transcript
00:10Assemblies to create the track corridor and we'll go over a few ways that we can do this.
00:15To create the corridor, we will go up to the corridor and choose corridor.
00:21In the corridor dialog, we will provide a name and choose the alignment and profile that we want to use.
00:30Then we'll pick the assembly and we can modify this later on.
00:34We won't pick a template. We don't have one of those set up at this time.
00:37And then we will choose the target surface.
00:41So in the parameters box, we can make changes to any of these items like the assembly or the profile.
00:49And we can refine the start and end station numbers and we can do that with the station picker.
00:55And we have marked a few breaks in our corridor that we'll pick for the end of our regions.
01:03In the frequency dialog box, we can determine how the corridor will process and which points will be targeted horizontally
01:11and vertically.
01:13In the target dialog, we can identify which alignments will represent the left and the right track and the profile.
01:21And we can do that by picking from the list of alignments or by choosing those in plan view.
01:28And we can determine the target surface under the surface tab.
01:33In this example, we will add regions after the first region and demonstrate this process.
01:40So we'll pick the assembly and let's choose this time a wall assembly.
01:45And the start station will automatically populate based on the previous region end.
01:50And we will use the tracking tool to determine the end station in our plan view.
01:55And we'll likely need to update the frequencies from the default set values.
02:00And we need to identify the target alignments for this region again.
02:04And we will need to do this each time we create a new region.
02:09And we can set up the frequencies and targets after all the regions have been added.
02:14But this process will take a bit longer for setting up the targets since there are so many different sub
02:20assemblies to choose from.
02:22And so with only one surface, it's much easier to determine the end conditions and the target surface.
02:29Once we're all set up, we can select OK and build the corridor.
02:33As we inspect the results of the corridor, we can view some of those transition areas.
02:38And to get a better view of the corridor in section view, we will select the corridor and choose section
02:44editor.
02:45In the section editor window, we can fix our view either on a set offset and elevation, or we can
02:52base it on our sub assembly.
02:55And in this view, it's somewhat difficult to see the layers with the grid pattern.
02:59So we can set our view options and change our style to all codes.
03:05And this will let us see the shaded sections.
03:09And we'll pick the sub assembly that we want to focus on, our double track section.
03:13Here, we can see different locations along the corridor, and we can inspect for any issues.
03:20So now let's create a corridor using a slightly different setup.
03:24We'll provide a name, the alignment, and the assembly.
03:29We'll define the begin and end station limits.
03:34We'll set the frequency and the target parameters.
03:39And we'll do those both in plan and in profile view.
03:46This time, in our corridor, we will choose to split our region.
03:51So let's do that.
03:52And we'll do that at all our defined transition locations.
03:58Those values will appear in our parameters window.
04:02Let's update each assembly for each region.
04:06Now the advantage of this method is that all of our targets inherit the first region
04:12and parameters that we set up.
04:14So if we know our typical section limits,
04:17or the location of where our regions will begin and end,
04:21this is a method that will save us a lot of time in our setup.
04:25One other element we want to look at is a target for our platform area.
04:29We previously created a sub-assembly in the last video,
04:33and we want to use the platform edge lines from our plan view.
04:37So we will pick our left side offset and elevation using our platform lines,
04:43both for inside and the outside.
04:46And we'll pick the right side as well with the same workflow.
04:50And now we run the corridor.
04:54And we'll take a look at our sections.
04:59In some transition areas, we might see where our corridors or feature lines
05:04don't behave the way that we want them to.
05:06In order to remedy this issue, we can adjust the station limits between the regions
05:11and create a very small gap.
05:13And in this case, we'll just use a few millimeters and rerun the corridor.
05:19Now when we review that, we can see those corridor lines are much cleaner
05:23near those transition regions.
05:25So next, let's create another corridor using our ballast only and the skeleton track assemblies.
05:31Now this is an easy way to model our corridor when the eastbound and westbound tracks have different
05:37cant values, which is pretty common.
05:40If needed, we can add cant to our center align alignment,
05:43and this will provide some super elevation for our ballast surface.
05:48Once we set that, we will set up our corridor the same way.
05:51This time, we will pick our ballast only for the assembly.
05:56And we can split our region.
05:58This time, we'll split it for the platform area.
06:02Now we need to add baselines for our track.
06:04So let's add the eastbound track first.
06:07And we'll define our profile.
06:09And we'll use the skeleton track assembly.
06:12So it will just show the rails and the ties.
06:16Then we'll add the westbound with the same parameters.
06:20And then we can build the track corridor.
06:23Now in section view, we can see the different cant values for eastbound and westbound.
06:30And we did this intentionally for this example.
06:32But as we move along the corridor through the sections, we can see the cant transition along our curves.
06:39One brief demonstration for corridors.
06:42When we set our targets on the rail alignments, the assembly will adjust to find that alignment.
06:49So if we adjust the location of our alignment and rebuild the corridor, we can see those updated changes, both
06:57in plan view.
06:58And we'll look at the same thing in our section view.
07:01And we can see how those transition together.
07:04Now let's create a corridor transition.
07:07We have an area with special track work where we want to create another area for the switch machine.
07:14And we want to do that on each side for this crossover.
07:17So we will select the corridor and pick corridor transitions.
07:21Here we'll define our baseline.
07:23In this case, it's the center line between our tracks.
07:25Then in the transition window, we can pick create a new transition set.
07:29Then we move the cursor in plan view.
07:32We can actually see the different assemblies highlight.
07:35So let's pick the double track assembly.
07:38And once we do that, we'll see the parameters that we can transition.
07:42And these could be horizontal or vertical elements.
07:45And there's a number to choose from.
07:47But let's pick the right ballast shoulder here.
07:50Next, that'll ask us to define our start station.
07:53And we can do that with the tracker.
07:55And we can input the beginning value.
07:57And it will tell us what that initial value is set at.
08:00And we'll keep that at 0.5 meters.
08:02And then we can pick the transition station and value.
08:06And this time, for the transition, we'll pick 2.5 meters.
08:09And this will be a linear transition.
08:11And then we can pick the next section with the offset values.
08:16And then the final section.
08:18And we'll provide the end transition numbers here.
08:21And if we need to adjust any of our station values, we can do that by inputting those values here.
08:26And we'll make these numbers easy.
08:28And we'll round up to the nearest 10.
08:30Then we'll choose Apply.
08:32Once we do that, we can see each section in our plan view.
08:36Or we can view the entire set.
08:39So now let's copy this for the other area.
08:42We'll give that a name first.
08:44And we'll lock it so that those transition spacings will stay the same.
08:49We'll paste that.
08:50And then we'll change the name for the left side.
08:53And here we need to transition for the left ballast shoulder.
08:58Now if we try and relocate the first position point on the tracker,
09:02we're limited to the end station of that first section.
09:07So let's pick the final value of our end transition.
09:11And pick the station we want in plan view.
09:14Now because we had it locked, all those values will update respectively.
09:18And if we adjust that station at the end, we can update those again.
09:23Then we'll pick Apply.
09:25And we can see the switch machine transition locations.
09:30Now let's look at a final example for a multi-track layout.
09:34We have a yard here.
09:36And we have it laid out with several different tracks.
09:38And they're all parallel.
09:41We've identified a midpoint between the tracks that we want to use in our sub-assembly.
09:47And it's a feature line.
09:48So we'll go through the same process to set up a new corridor.
09:52Now in the ladder area, we want to use a two-track layout.
09:57And we'll pick the yard lead as the left track.
10:02And the main line as the right track.
10:07In the middle section, we want to use a single track region for the main line.
10:12And we'll use that as our right track.
10:15Then we can close the ladder the similar way that we started it, with a double-track region.
10:20Now let's build this right now.
10:21In the ladder area, we'll use skeletonized track for our layout based on the alignment and the profile.
10:27We also want to add a baseline for each track.
10:33And then we'll define the station limits for each region.
10:36And in this middle section for our interior tracks, we need to use those feature lines to define the edges
10:44of our ballast.
10:45And we'll do this for each track in the yard.
10:49And once we rebuild that corridor, we can view that in the section view.
10:54And we can see those ballast sections line up very nicely.
10:57And we can see how that ladder transitions for each area as we pan through those sections.
11:06The last thing we'll look at is adding pay items to our corridor.
11:10So under the Analyze tab, we can select the QTO Manager.
11:14This tool allows us to add pay items to our content in our CAD file.
11:19Now we could use the default values, but we have a pay item CSV in our project directory.
11:26And so we'll load that here.
11:28And then we'll add the categorization file from the same directory.
11:33And this will show us all the pay items that we can assign to the different objects in our file.
11:40To add this data to a corridor, we'll select the corridor and pick corridor properties.
11:46And we need to define these pay items in our code sets.
11:50So we'll go to the code tab.
11:52And when we view our codes, we'll see that there are no pay items defined in our list.
11:57So we need to edit those codes.
11:59And we'll select that here.
12:00And under the links and the points, we can define the different elements of our corridor,
12:06such as the ballast or the track, that may need a required pay item number.
12:12So now when we select takeoff quantities, we can calculate the values and see what is derived from our corridor.
12:21So these are just a few different ways that we can set up and create a corridor for rail and
12:27track
12:27property.